As an important equipment in the power distribution system, the ring main unit is widely used in urban power supply, industrial power supply and building power distribution. In order to ensure the safety, reliability and long-term stable operation of the ring main unit, special attention should be paid to the following aspects during the installation process:

1. Selection of installation environment

The installation environment of the electrical ring main unit has a direct impact on its performance. When choosing the installation location, the following factors should be considered:

- Ventilation conditions: Ensure that the rmu has sufficient heat dissipation space to avoid overheating.

- Humidity and temperature: Avoid installing the rmu in a high humidity, high temperature or corrosive environment.

- Dustproof: The installation location should be away from dust and dirt to prevent affecting the normal operation of the equipment.

2. Foundation and support

The foundation of the rmu panel should be stable and able to bear the weight of the equipment. During installation:

- Check the strength and uniformity of the foundation to ensure that there is no settlement.

- Use a level to correct the levelness of the rmu to avoid equipment failure caused by tilting.

3. Electrical connection

When making electrical connections, relevant electrical safety regulations must be followed:

- Make sure to make connections in a power-off state to avoid the risk of electric shock.

- Use wires of appropriate specifications to ensure current carrying capacity.

- Check the grounding system to ensure good grounding to improve safety.

4. Equipment protection

The protection level of the ring network cabinet should meet the actual application requirements:

- Ensure that the door lock and sealing performance are good to prevent water and dust from intruding.

- Configure necessary protection equipment as needed, such as overload protection and short-circuit protection devices.

5. Labeling and warning

After installation, the ring network cabinet should be clearly labeled:

- Attach operating instructions and warning signs to the cabinet to remind operators to pay attention to safety.

- Indicate the functions and connection methods of each electrical interface for future maintenance and repair.

6. Testing and debugging

After installation, comprehensive testing and debugging must be carried out:

- Check the correctness of all electrical connections to ensure that there is no short circuit or poor contact.

- Perform load testing to ensure that the ring network cabinet operates normally under various working conditions.

7. Regular maintenance and inspection

After the outdoor rmu is installed, regular maintenance and inspection are the key to ensure its normal operation:

- Regularly check the sealing and protective performance of the cabinet.

-Regularly clean and inspect the internal components to ensure that there is no dust accumulation and corrosion.


Get in touch

CONTACT US
Copyright © 2007-2024 Delixi Electric All Rights Reserved.    浙ICP备13001006号-1  浙ICP备13001006号-3  Sitemap

LEAVE A MESSAGE

Contact us!
We're not around but we still want to hear from you! Leave us a note:

* indicates a required field